Project Impact

Last updated: 30.09.05


Together Ensuring Childrens Safety (TECS), Malawi


Overall
amount


Population
target


Target
region

USD 2'245'000

11'500 adults and
5'500 children

60 villages in 2 districts
(Dowa and Kasungu)



Project
period






Activities


Target

     
Number of villages
Total Land Care
TLC
Small scale irrigation: pumps
 
Small scale irrigation: irrigated hectarage

Agro-Forestry practices: nurseries
 
Agro-Forestry practices: trees planted
 
Soil conservation: contour ridging
 
Soil conservation: gully control
 
Soil conservation: vetiver nurseries
 
Soil conservation: contour vetiver hedgerows

Training of community leaders
Rehabilitation of school blocks
Creative Center for Community Mobilisation
Construction of classroom school blocks
CRECCOM
Construction of teachers' houses
 
Construction of permanent pit latrines
 
Procurement of desks
 
Establishment of model school gardens

Targeted communities
Nkhoma Synod
Formation of well committees
 
Wells constructed
 
Maintenance team, water sanitation team and leadership training

CANCELLED
  • The Health component of the project was cancelled

  • The allocated funding for the Health component that will be partly used for 12 boreholes will be built to improve access to water, until June 2006

 

MID-TERM EVALUATION

Carried out in December 2006, please see here


FINAL EVALUATION

The Final Evaluation will be carried out in November/December 2005

NOTES
FOOD SECURITY and AGRO-FORESTRY

Small-scale irrigation

  • 226 households received a treadle pump and input pack, for a total of 499 farmers participating, 4 of which were bought by farmers using revolving funds.


SOURCE INFORMATION DATE
  • Factsheet update from TECS, September 2005

  • TECS 2004-2005 Annual Report, September 2005

Numbers are to be used with caution; they are provided as quantitative measurement at a given time. Communities’ changes of attitude concerning child labour are difficult to quantify.

Legend

Improved progress compared to last factsheet

No progress compared to last factsheet

Decreased progress compared to last factsheet

Progress beyond target was made